i) Estimated Cost for a New Kindergarten Building for 'Uiha, Ha'apai, Tonga Islands.
Description | Amount (TOP$) | |
| Preliminaries (transport, machine hire ...etc) | 5,500 | |
| Foundation/Footing | 8,215 | |
| Timberworks | 15,084 | |
| Linings | 12,520 | |
| Roofing | 2,456 | |
| Nail | 1,113 | |
| Doors/Windows | 3,150 | |
| Hardware Materials | 7,241 | |
| Labour Costs | 8,600 | |
| Contingency | 2,000 | |
| Total Estimated Cost | (TOP)$65,880 |
ii) Estimated Cost for a Guest Fale - (a revenue generating idea to meet the oprational costs of running the Kindergarten).
| Description | Amount (TOP$) | |
| Premilinaries | 2,500 | |
| Foundation/Footing | 3,363 | |
| Timberworks | 8,080 | |
| Linings | 8,130 | |
| Roofing | 1,680 | |
| Nail | 705 | |
| Doors/Windows | 640 | |
| Hardware Materials | 5,830 | |
| Labour Costs | 2,000 | |
| Contingency | 1,000 | |
| Total Estimated Cost | (TOP)$33,928 |
*These are estimated costs quoted by a local registered architec. This is to give an idea of what the project may cost. And brief breakdown of the costs.